{"id":5883,"date":"2021-10-01T08:46:58","date_gmt":"2021-10-01T15:46:58","guid":{"rendered":"https:\/\/unitedconstruction.com\/?p=5883"},"modified":"2021-10-11T10:37:51","modified_gmt":"2021-10-11T17:37:51","slug":"autumn-progress-is-afoot-at-swope-middle-school","status":"publish","type":"post","link":"https:\/\/unitedconstruction.com\/autumn-progress-is-afoot-at-swope-middle-school\/","title":{"rendered":"Autumn Progress is Afoot at Swope Middle School"},"content":{"rendered":"
This Fall will welcome swift and notable progress at Swope Middle School, as both expansions and new construction continue to go smoothly and efficiently.<\/p>\n
\u201cWith the new season comes new milestones at Swope,\u201d said Casey Gunther, Operations Manager for United Construction. \u201cStudents and staff will be excited to learn that several facilities will be ready to use in the coming weeks, including the new gym. We look forward to even more progress as Fall continues on.\u201d<\/p>\n
Site crews have completed excavations at the location of the new two-story classroom building. Workers continue to make progress as the underground utilities are near completion. When finished, the building will house a new resource center, math and science classrooms, a technology lab, a new teachers\u2019 lounge and workspace, social science and language classrooms, a group room for various activities and a hub space.<\/p>\n
The remodel and expansion of the kitchen facilities are progressing and making great headway. Additionally, the new gymnasium will be ready for games at the beginning of October, where students can enjoy the revamped basketball hoops, volleyball courts and a scoreboard. The new fitness center will also be ready to use soon.<\/p>\n
More concrete slabs will be poured at various locations throughout the month of October. Setting of concrete masonry unit (CMU) block walls will follow directly after the pours are complete and will continue until the end of the calendar year.<\/p>\n","protected":false},"excerpt":{"rendered":"
This Fall will welcome swift and notable progress at Swope Middle School, as both expansions and new construction continue to go smoothly and efficiently. \u201cWith the new season comes new milestones at Swope,\u201d said Casey Gunther, Operations Manager for United Construction. \u201cStudents and staff will be excited to learn that several facilities will be ready to use in the coming weeks, including the new gym. We look forward to even more progress as Fall continues on.\u201d Site crews have completed excavations at the location of the new two-story classroom building. Workers continue to make progress as the underground utilities…<\/p>\n","protected":false},"author":5,"featured_media":5884,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"nf_dc_page":"","_exactmetrics_skip_tracking":false,"_exactmetrics_sitenote_active":false,"_exactmetrics_sitenote_note":"","_exactmetrics_sitenote_category":0,"footnotes":""},"categories":[1,97],"tags":[57,178,49,46,115,23,168,137,114],"class_list":["post-5883","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-news","category-project-milestone","tag-build-united","tag-classrooms","tag-cmar","tag-expansion","tag-news","tag-projects","tag-remodel","tag-swope-middle-school","tag-united-construction-company"],"yoast_head":"\n